1. Find the schedule and cost variances for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000. Show work and provide a detailed explanation of the results.

Respuesta :

Otras preguntas

Need help!!!! How do you prove two circles are similar?
A 12-foot high ladder reaches a tree limb when it leans at a 36 degree angle with the ground. Approximately how far away is the base of the ladder from the tree
what is the value of 1 in 10374
Question 1 Compare neap and spring tides. Give two comparisons in your answer. Question 2 Which of the following best describes what causes the tides? The gravi
prewriting is valuable because it
What type of triangle is formed by joining the points D(7, 3), E(8, 1), and F(4, -1)?
what is the improper fraction 17/10 as a decimal
A circle has its center at the center of a square with 6-inch sides. Find the area of the square not covered by the circle. Round the answer to the nearest tent
log9(x+6)-log9x=log9 2
(a - b)(a 2 + ab + b 2)