Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team True False

Respuesta :

Emhicee
Emhicee Emhicee
  • 26-01-2020

Answer:

False

Explanation:

Resource leveling in project management is a technique used to ensure that over-allocation of resource or conflicts as a result of over-allocation does not occur.

Cheers

Answer Link

Otras preguntas

suppose the government places a 5 per unit tax on a good, what the surplus after this tax?​
math question thanks if you help!
A student notices that the saucer below a coffee cup becomes warmer after coffee is poured into the cup. Energy was transferred from – the cup to the saucer by
A rectangular garden is 10 ft longer than it is wide. Its area is 1575 ft. What are its dimensions? W= L=
Find the Size of angle YZX give your answer to 3 significant figures
there are 3.45 moles of (NH4)2 SO4, how many grams is this?
Two baddies of equal masses move with uniform velocities V and 2V respectively.The ratio of their kinetic energies
Increase 100kg by 10%
What is the coefficient and constant of 3c + 4
how to make a simple tester​