Answer:
a. Rp= 10.0hr
b. Tc= 1052 workers
c. n= 421 workstations
Explanation:
(a) Rp= Da/250Hsh. Rearranging, Hsh= Da/250Rp= 150,000/250(60) = 10.0 hr
(b) Tc= 60E/Rp= 60(0.95)/60 = 0.95 minTs= Tc– Tr= 0.95 – 0.10 = 0.85 minw= Min Int 14.0(60)/0.85(0.94) = 1051.3 rounded up to 1052 workers
(c) n= w/M= 1052/2.5 = 421 workstations