It took 6 people 4 days to complete a concrete project. How many days will it take 2 people to complete the job?

It took 6 people 4 days to complete a concrete project How many days will it take 2 people to complete the job class=

Respuesta :

josueruiz80 josueruiz80
  • 26-03-2020

Answer: 1.3

Step-by-step explanation:

So if there are 6 people the first time to complete the job, then there are 2 . we need to divided the 6 by 2 to find out how many days it takes, so it is 3. We divided the 4 days by 3 and we get 1.3 so it takes 1.3 days for 2 people to complete the job.

Answer Link

Otras preguntas

What is a scientific theory
What did Tom bring east with him that made bici realize how much money he really had ?
how is vodoo religious syncretism
Students in a classroom have eaten 20% of jellybeans from a jar. There are now only 100 jellybeans left! How many jellybeanswere in the jar to begin with?​
Explain for me the graphic transformation
Write a function g whose graph represents the indicated transformation of the graph of f. f(x) = 4–1 +11
write five important facts from the constitutional convention ​
what is the material in the center of most of your bones and what does it do?
Label them plzzz!!!!!
Football A football team loses 8 yards on each of 3 consecutive plays. Find the total change in yards from where the team started.The total change is yards.